Public Service Commission

Projects

Division PSC
Project / Program purpose and objectives The PSC’s new ITS system aims to efficiently and securely allow PSC staff to enter, share, and manipulate data. It is utilizing the talents of SITSD to produce a flexible, reliable system that lets staff better serve the public, businesses, and fellow employees.
IT Goal and Objective Reference 1
Estimated start date 3/1/2018
Estimated deliver date 6/30/2019
Estimated cost $426,400
HB 10 Request No
Funding Sources HB2: $426,400
Annual costs upon completion
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. Project completed, trouble shooting and updates are ongoing. 110% of funds have been spent.

Division PSC
Project / Program purpose and objectives The new website will act as a portal for public and private entities to interact with the PSC in a safe and efficient manner. It is working with SITSD to ensure all aspects of the website conform to state best practices.
IT Goal and Objective Reference 2 and 3
Estimated start date 10/1/2017
Estimated deliver date 4/30/2019
Estimated cost 20,000
HB 10 Request No
Funding Sources HB2: 20,000
Annual costs upon completion 20,000
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. Complete, 100% of funds expended.

Agency Contact Information

Agency Director / Administrator
Mandi Hinman
444-6175
mhinman@mt.gov
PO BOX 202601 1701 PROSPECT AVE HELENA, MT 59620-2601 United States
Information Technology Contact
(CIO / IT Manager)
Phillip English
444-6172
penglish@mt.gov
PO BOX 202601 1701 PROSPECT AVE HELENA, MT 59620-2601 United States
Information Security Manager
Phillip English
444-6172
penglish@mt.gov
PO BOX 202601 1701 PROSPECT AVE HELENA, MT 59620-2601 United States