Division | PSC |
---|---|
Project / Program purpose and objectives | The PSC’s new ITS system aims to efficiently and securely allow PSC staff to enter, share, and manipulate data. It is utilizing the talents of SITSD to produce a flexible, reliable system that lets staff better serve the public, businesses, and fellow employees. |
IT Goal and Objective Reference | 1 |
Estimated start date | 3/1/2018 |
Estimated deliver date | 6/30/2019 |
Estimated cost | $426,400 |
HB 10 Request | No |
Funding Sources | HB2: $426,400 |
Annual costs upon completion | |
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. | Project completed, trouble shooting and updates are ongoing. 110% of funds have been spent. |
Division | PSC |
---|---|
Project / Program purpose and objectives | The new website will act as a portal for public and private entities to interact with the PSC in a safe and efficient manner. It is working with SITSD to ensure all aspects of the website conform to state best practices. |
IT Goal and Objective Reference | 2 and 3 |
Estimated start date | 10/1/2017 |
Estimated deliver date | 4/30/2019 |
Estimated cost | 20,000 |
HB 10 Request | No |
Funding Sources | HB2: 20,000 |
Annual costs upon completion | 20,000 |
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. | Complete, 100% of funds expended. |