Division | Waste Management and Remediation |
---|---|
Project / Program purpose and objectives | Replace the case management system for waste management and remendatiion. |
IT Goal and Objective Reference | Goal 3 |
Estimated start date | 1/23/2012 |
Estimated deliver date | 8/30/2012 |
Estimated cost | 5,344,000 |
HB 10 Request | No |
Funding Sources | Long Range: 2724000 State Special: 1880000 Federal Special: 40000 |
Annual costs upon completion | NA |
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. | Complete. $4,502,764 |
Division | Water Quality |
---|---|
Project / Program purpose and objectives | Create a fee system for part of the Water Quality division. |
IT Goal and Objective Reference | DEQ 3 |
Estimated start date | 6/3/2015 |
Estimated deliver date | 6/30/3019 |
Estimated cost | 1,199,467 |
HB 10 Request | No |
Funding Sources | State Special: 1157488 Long Range: 350000 |
Annual costs upon completion | NA |
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. | Complete. $1,559,465 |
Division | Air, Energy, and Mining |
---|---|
Project / Program purpose and objectives | Port Montana's Coal ePermitting for Federal Use |
IT Goal and Objective Reference | NA (Started before reported plan) |
Estimated start date | 6/27/2016 |
Estimated deliver date | 6/28/2019 |
Estimated cost | 1,750,000 |
HB 10 Request | No |
Funding Sources | Federal Special: 1400000 Long Range: 350000 |
Annual costs upon completion | Unknown |
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. | State of Montana work complete. State of Montana now acts as a fiscal agent. $68,973,002 (This includes non-Montana sources). |