Update: Initiated Phase 1 Database and Lobbyist Application Modernization (DLAM) March 2020. Replacement of Oracle system was considered, however, modernizing the current Oracle database and applications was more time and cost effective approach.
Objectives
-
Secure funding needed to develop new system as per the quote generated by SITSD.
Update: SITSD secured funds 2019 legislative session.
-
Engage SITSD to develop and deploy new system.
Update: Worked with SITSD to secure Sapiens (Formally Stone River) as vendor for Database and Lobbyist Modernization (DLAM) project February/March 2020.
-
Transition away from the current Oracle system to the new system developed by SITSD
Update: Sapiens initiated Database and Lobbyist Modernization (DLAM) project March 2020 with Phase 1 completion date scheduled for November 2020 and Phase 2 completion June 2021
-
Add two new drawers to the Perceptive Content system for storing imaged lobbying and principal
files.
Update: Completed Perceptive Content hard copy system for Lobbyist and Principal storage in 2019. STISD moving from Perceptive to IBM system Fall of 2020, initiated transfer process July 2020.