Division | OCHE Benefits |
---|---|
Project / Program purpose and objectives | Benefits online enrollment system |
IT Goal and Objective Reference | Goal 3 |
Estimated start date | 1/2/2018 |
Estimated deliver date | 7/1/2019 |
Estimated cost | Approximately $655,425 over three years |
HB 10 Request | No |
Funding Sources | Benefits Insurance Fund: |
Annual costs upon completion | none |
Status of the project as of March 31, even numbered years. Indicate % completed and status of funds expended. | 100% complete. We have now been through 2 successful enrollment periods. The software is in use by all campuses and improvements in reporting and administration have been realized through the project. The majority of funds have been used for the implementation and 2 years of annual maintenance. |